Monday 4/9

  • Preliminary Research 
  • Decide one topic to address
  • Order parts

Monday 4/16

  • Continue Preliminary Research 

Monday 4/23

  • Have all parts 
  • Run Tests on Equipment.
  • Install Windows 7 on my Laptop

Monday 4/30

  • Have main Robotic element constructed 
  • Have Basic Test Code
  • NEXT WEEK’S CODE GOAL: Begin Solving Serial Port Issue

Monday 5/7

  • Circuit board completed. 
  • Everything is wired.
  • NEXT WEEK’S CODE GOAL: Face Tracking

Monday 5/14

  • Have Final Body for Robot completed. 
  • Continue to work on code
  • NEXT WEEK’S CODE GOAL: Record videos 

Monday 5/21

  • CODE COMPLETE. 
  • Begin walking with Robot.
  • Acquire a friend to assist with documentation video
  • Start Editing Video

Monday 5/28

  • Continue Robot Walks & Documentation
  • Edit video after completing walks.

Monday 6/4 - I’D BETTER BE DONE.